How much deposit can a tradie ask for? A state-by-state guide

A homeowner and a builder in hi-vis reviewing a building contract with a calculator on the verandah of a weatherboard house, with a timber-framed extension under construction behind them.
In this article

Before a builder or tradie starts a job, they'll often ask for a deposit. That's normal, especially when materials have to be ordered. But for home building work, most states and territories put a legal cap on how much can be asked for up front, and some link the cap to the size of the job.

This guide covers domestic and residential building work in each state and territory. Check the rules for your type of work, the contract price and any exceptions before you sign or pay.

Why are deposits capped?

A deposit is money paid before any work has been done. If the business disappears, goes broke or never turns up, that money can be hard to get back. Caps limit how much you have at risk, and in several states, paying more than the legal maximum can also reduce what you can recover through home warranty insurance. QBCC and NSW Fair Trading both warn about this.

After the deposit, payments should generally reflect the work completed. For example, for Queensland contracts over $3,300, QBCC says the contractor can’t claim more than half the price, including the deposit, before at least half the work on site is complete.

How much deposit can a builder ask for in Victoria?

Under Victoria's Domestic Building Contracts Act 1995, Consumer Affairs Victoria says a deposit can be no more than:

  • 10% if the total contract price is less than $20,000

  • 5% if the total contract price is $20,000 or more.

Contract: You need a major domestic building contract for most domestic building work worth more than $10,000.

Victoria’s deposit and major contract rules are due to change on 31 March 2027. Until then, the caps above apply. The reforms raise the major contract threshold from $10,000 to $20,000 and change deposit caps based on how much work is made off site or uses other modern construction methods. Separately, Victoria’s Home Warranty scheme applies to eligible work valued at more than $20,000 under eligible contracts signed from 1 July 2026. Check with the Building and Plumbing Commission about cover for a lost deposit.

What's the maximum deposit in New South Wales?

NSW caps the deposit at 10% of the contract price for residential building work covered by the rule. An exception applies to stand-alone specialist work, such as electrical or plumbing work that forms no part of other home building work.

Contract:

  • Jobs over $5,000 (including GST) need a written contract.

  • Jobs over $5,000 and up to $20,000 need a small jobs contract.

  • Jobs over $20,000 need a more detailed large job contract, with a cooling-off period of five clear business days.

Insurance first: If the job needs Home Building Compensation cover, the contractor must give you the certificate before asking for a deposit. This generally applies to residential building work over $20,000. You can check the certificate through Service NSW.

What deposit can a QBCC licensed contractor ask for in Queensland?

The QBCC sets the maximum deposit by contract value:

  • $3,300 or less: 20%

  • Over $3,300 and under $20,000 (level 1 contract): 10%

  • $20,000 or more (level 2 contract): 5%

A deposit of up to 20% is allowed in limited cases, where customised building work or prefabrication done away from the site makes up more than 50% of the total contract price. QBCC's examples include made-to-measure kitchen modules or cabinetry, windows, sheds, pergolas and cladding.

Queensland requires a written contract for domestic building work over $3,300. Level 1 applies above $3,300 and below $20,000. Level 2 applies from $20,000, and the contractor must give you the QBCC Consumer Building Guide before you sign.

How much deposit can a builder take in Western Australia?

Building and Energy says the maximum upfront deposit is 6.5% for fixed-price home building contracts from $7,500 to $500,000, subject to the cabinetry exception below. Contracts outside that range sit outside this cap.

There's one exception. For cabinetry work where the off-site part is more than 50% of the contract value, a deposit of up to 20% can be requested.

Contract: Contracts must be in writing and signed by both parties.

Insurance: Home indemnity insurance is required for building work that needs a building permit and is valued at more than $20,000. It can cover loss of a deposit up to $40,000. Don't make payments until it's in place.

What are the deposit rules in South Australia?

For domestic building work priced at $20,000 or more, South Australia caps the deposit at 5% of the contract price. The $20,000 threshold for the current rules took effect on 10 November 2025.

  • For work under $20,000, check the terms in writing. South Australia treats this as minor domestic building work and the same deposit cap does not apply.

  • Other permitted payments on covered contracts can include genuine progress payments and costs such as surveying or building indemnity insurance.

Contract: For work priced at $20,000 or more, get a signed written contract and a copy of the building contract rights notice. You normally have five clear business days after making the contract to withdraw.

How much deposit can a builder ask for in Tasmania?

Tasmania’s Residential Building Work Contracts and Dispute Resolution Act 2016 generally applies to residential building work priced at $20,000 or more. The Act and the 2026 regulations set these maximum deposits for covered contracts:

  • 10% for covered contracts under $50,000

  • 5% for contracts of $50,000 or more

  • 20% for a covered contract if the value of off-site work exceeds half the contract price.

Contract: All contracts must be in writing, dated and signed by both parties. You can withdraw within five business days of receiving the signed contract and the guide.

What about the Northern Territory?

In the NT, a written residential building contract is required for prescribed residential building work. The deposit is capped at 5% of the total contracted price. If you agree on an alternative progress payment schedule, use the required forms to record it.

Builders also need a fidelity fund certificate for prescribed residential work before they can demand payment from you. This includes building work over $25,000 that increases a home's floor area.

Is there a deposit cap in the ACT?

The ACT Government says there is no legal cap on the initial deposit. Agree on the amount and payment stages in writing. The ACT guidance says you may be able to recover up to $10,000 under the project’s insurance if the work is not completed. Check the policy or fidelity fund certificate before paying.

What should I check before paying a deposit?

  1. Check the licence. Look the business up on your regulator's register and make sure the name matches your quote or contract. Our guide Does this job need a licensed tradie? links to each register.

  2. Get it in writing. Even below the thresholds, a written quote or contract with the price, scope and payment stages protects both sides.

  3. Check the deposit against the cap. Work out the percentage yourself. If it's over the limit, query it. QBCC says you're not obliged to pay more, and it may be a red flag.

  4. Ask for the insurance certificate. Where the project needs home warranty or domestic building insurance, check the certificate covers the right address and builder. In NSW, you must receive it before the contractor can ask for a deposit on work that requires cover.

  5. Watch for separate "plans" agreements. NSW and WA both warn that upfront payments for plans or preliminary work under a separate agreement may not be covered by home warranty insurance.

  6. Pay into a business account and get a receipt. Keep a record of every payment.

  7. Don't pay ahead of the work. After the deposit, only pay for completed stages or work actually done.

Find a local tradie

You can browse building and renovation businesses on TradeBench. Before you sign anything, check their licence and ask how their deposit and payment stages work.

This article is general information only and isn't legal advice. Deposit caps, thresholds and insurance rules change, so check with your state or territory regulator before you sign a contract or pay a deposit.

FAQs

Can a tradie ask for 50% up front?

Usually the cap is much lower on work covered by a state or territory deposit rule. Check your jurisdiction, contract price and type of work. The ACT has no initial deposit cap, and WA’s 6.5% cap applies only within the contract range above.

Does the deposit cap apply to small jobs?

It depends on the work and jurisdiction. Queensland’s general cap is 20% at $3,300 or less. NSW’s 10% cap can apply even when the job is too small to require a written contract, subject to exceptions. The WA fixed-price cap starts at $7,500, and the rules covered here for SA and Tasmania generally start at $20,000.

What if I've already paid more than the maximum?

Contact your state regulator for advice. QBCC warns that if you pay more than the lawful deposit, you won't be able to recover the excess through the Queensland Home Warranty Scheme.

Is a deposit the same as a progress payment?

No. A deposit is paid before work starts. Progress payments are paid as stages are completed and should match the work done.

Explore these topics

Put it into practice

Explore businesses in categories connected to this topic.

Explore the directory

Recently published businesses in these categories. Browse profiles to find the right fit.

Find businesses near your project

Choose a trade or supplier and search by their base suburb or postcode.

Run a trade or supply business?

Give people a place to discover your business, explore your services and get in touch.

List your business

Keep reading

More from Article Hub to explore next.

Browse all articles